Chapter 10.
Project Approval
10.1 Introduction

Project approval is required before CIDA can invest funds in a specific initiative. Approval authorities vary depending on the value of the project. This chapter provides an overview of the documentation required for project approval and indicates the various project approval authorities.

Notes:
§ Project Approval, Executing Agency/Implementing Organization selection, and contract/contribution agreement signature authorities are different and distinct.
§ If the Project Manager (PM) is seeking a directed sourcing selection, a project can not be approved without the prior selection approval of the proposed Executing Agency (EA) or Implementing Organization (see the Contracting Guide for Managers in CIDA).
§ Projects can not be submitted for approval until an environmental assessment, if legally required, is conducted under the Canadian Environmental Assessment Act (CEAA) and a decision is taken regarding significant adverse environmental effects (see the CEAA and the Roadmap).

Helpful Hints:
Other steps in the project cycle may be undertaken in parallel with the preparation of the Project Approval Document (PAD). These include: consultation with Legal Services regarding project agreements (Chapter 11); and, preparations for consultant selection (see the Contracting Guide for Managers in CIDA). Undertaking these preparatory activities in parallel will help to save time in operationalizing the project.

The Project Approval Document (PAD), prepared by the PM in consultation with the project team, is the document which defines the project, including the expected results, performance indicators, critical assumptions, budget, schedule, risks, implementation methodology, etc. and seeks approval for funding.

The approval of a project is the official authority to encumber funds against the project.

The Project Approval Document defines the scope of the project and the parameters for project implementation. The PAD must demonstrate that the project meets the project appraisal criteria and must demonstrate links with the Country/Regional Programming Framework (C/RPF) (see Chapter 6) or the overall CIDA policy framework (see Chapter 2) and/or branch programming framework, if no programming framework exists.

There are two formats for project approval documentation:

Approval for Special Program and Project Expenses (SPPEs) and Canada Fund for Local Initiatives Projects is briefly discussed in section 10.4 below.

10.2 Project Approval Documentation for Projects Over $500,000

Note:
The PAD must provide sufficient information and detail to allow the approving authority to make an informed decision regarding the investment of Canadian funds.
Project Approval Documentation1 for projects over $500,000 consists of:

Decision Memorandum* (2 pages maximum).
This memorandum is addressed to the Minister or Vice-President depending upon the value of the project. The headings within the Memorandum are: Subject; Decision Requested; Background; Consultation within Canada; Communications; and Recommendation.

The Decision Memorandum should clearly indicate how the decision requested is consistent with the C/RPF and the foreign policy statement, both in relation to the specific commitments set out for development assistance and to the broader foreign policy objectives (advancing prosperity, security and culture and values). The section on consultations should highlight discussions with other Canadian stakeholders and other federal departments. If no consultation has taken place, that should be indicated.

  1. development context and links between the project and the C/RPF or the overall CIDA policy framework and/or branch programming framework, if no programming framework exists;
  2. expected results (Outcomes and Outputs);
  3. project description: scope, timeframe, cost, an indication as to whether the proposal was developed by CIDA or submitted as an unsolicited proposal (under the Bilateral Responsive Mechanism - LOB 8), involvement of recipient country partners and stakeholders, and confirmation that the appropriate CIDA Project Management Strategy and Contracting Plan have been prepared;
  4. lessons learned (from earlier phases, similar projects or other initiatives in the same country or with the same partner by CIDA or other donors);
  5. expected benefits to Canada and the recipient country;
  6. anticipated risks based on information gathered during the various project analyses. This short section includes any questions or issues on recipient country ownership and project sustainability. The risk findings from all analyses are also compiled and analyzed in a Summary of Risks which is part of Item E (Annex C) below. Potential risks are also listed in the LFA (see Chapter 5);
  7. program financial context.
C. Annex B* - Selection
(not required if selection competition will be through the open bidding system).
J. Indicative Planning Figures (IPF) Summary

The following documents are also prepared, as appropriate. Although they are not submitted to the Vice-President as part of the Project Approval Document package, their existence is confirmed in Section c) of Annex A of the PAD dealing with the project description:

For projects up to $500,000, Project Approval Documentation consists of:

A. PAD Cover Sheet (generated by the AIS)

B. A Decision Memorandum (2 pages maximum). This memorandum is normally addressed to the Director General or Program Director. The headings within the Memorandum are:

C. Annex A - Logical Framework Analysis (which emphasizes results sought, resources to be consumed and risks anticipated (see Chapter 5). As indicated above, the LFA is a key approval document for projects up to $500,000 and information provided in the LFA is not duplicated in the Decision Memorandum.)

D. Annex B - Project Budget by result, if possible, or by input (including annual cash flow with inflation adjustment, contingency and a Risk Allowance, if requested. The project budget is placed immediately after the LFA to make a direct link between the expected results and the resources and activities required.)

E. Financial Check List Form - CIDA 1082 or 1083

F. Selection Annex - if required

G.Gender Equality Form - CIDA 966

I. Environmental Screening Forms as required (CIDA 1519-1 and others)

The following documents are also prepared, as appropriate. Although they are not submitted to the Director General or Program Director as part of the Project Approval Document package, their existence is confirmed in Section c) of the Decision Memorandum dealing with the project description:

10.4 Approval of SPPEs and Canada Fund for Local Initiatives Projects

The approval process for SPPEs and Canada Fund for Local Initiatives Projects are as simple as possible due to the nature of the proposed activity.

10.4.1 Approval of SPPEs3

SPPEs are described in section 4.3.4. Approval of an SPPE is in accordance with the delegated project approval authorities in section 10.6 and obtained through the simplified process described below, except when the request for funding is part of a Concept Paper, in which case the Vice-President will approve the SPPE (see section 7.4).

For other requests for the approval of SPPEs, the PM prepares a short Decision Memorandum to the appropriate Director General or Program Director which indicates:

The Decision Memorandum must be accompanied by a coversheet (generated by the AIS) and an (Environmental) Preliminary Assessment Form (CIDA 1519-1) (see Chapter 8 and The CEAA and the Roadmap).

The Director General or Program Director approves the SPPE by so indicating on the Decision Memorandum. (Contact your Strategic Management Division for more details.)

10.4.2 Canada Fund for Local Initiatives Projects (Canada Funds)

Canada Funds are described in the Guidelines for the Canada Fund for Local Initiatives which indicate the objectives, policy, procedures, eligible recipients, etc. for Canada Fund activities.

CIDA has the authority to allocate funds for, and to audit and evaluate projects of, Canada Funds. However, responsibility and accountability for Canada Fund sub-projects is delegated to the appropriate Canadian Post accredited to the recipient country. The Head of Mission is directly accountable to the President of CIDA for all matters relating to the Canada Fund. Although Canada Funds are financed out of bilateral program funds, they are not considered normal bilateral projects and do not require agreement with the recipient country.

In view of the unique nature of the Canada Funds (including the requirement for yearly funding approvals), the Vice-President, in consultation with the Head of Mission, decides on the amount to be allocated for the recipient country before the beginning of each fiscal year.

The allocation decision is often accomplished through one decision document for all Canada Fund programs within the Branch and the decision is communicated to staff, Finance Division, the Department of Foreign Affairs and International Trade (DFAIT) and each Canadian Mission concerned by memo or email.

10.5 Coding of Projects

The Agency has a single corporate coding framework based, where possible, on international coding standards. The coding of project information allows CIDA to develop consistent and reliable corporate reports as well as meet its reporting obligations to external stakeholders such as Parliament and the Development Assistance Committee (DAC). The coding framework consists of a number of coding tables corresponding to the Agency Information System (AIS) modules. The tables which are used to classify project details are identified below by the nature of the information.

In order to ensure that reports accurately reflect a country program's activities, project information should be entered into the AIS as early as possible. As a general rule, projects should be entered at the tentative stage in the AIS when the country program begins expending time and effort on the initiative and serious discussions are being held with projectpartners. Some specific principles are:
  1. if the project is being discussed as part of the country program's workplanning exercise and briefings with the Vice President, it should be entered in the AIS;
  2. if a formal request has been received from a recipient country and the country program is considering the proposal, it should be entered in the AIS;
  3. no project should be included in the country program's pipeline posted on CIDA's website, unless it has been entered in the AIS; and,
  4. if serious consideration is being given to a proposal received under the bilateral responsive mechanism, it should be entered in the AIS.
However, it is not usually possible to bring significant external factors into the project's manageable interests either due to limited project resources or to the very nature of the external factor. Therefore, the project should include a risk allowance and the PM, project team and other project stakeholders must monitor (not manage) risks using risk indicators as described in section 5.3 of  The Logical Framework: Making it Results-Oriented.
The risk allowance is a discrete budgetary component included in the initial project approval to compensate for the occurrence of specific, named events outside the control of CIDA or the Executing Agency and which, if they occur, will have an impact on the resources required to achieve the expected project results. The external risks MUST be identified and costed at the time of initial project approval.